Concrete Pour – Argos Therapeutics
Argos Therapeutics Bio-manufacturing Facility
The facility will support operations such as process manufacturing, mechanical, material management, laboratory, quality assurance, quality control and administration headquarters programmed space. The proposed facility will be fixed on 11.135 acre site.
Concrete slab pours / placements are scheduled to be done in 6 sections with approximately 1 week between pours. The first floor, 97,500 SF, will require 3 pours running west to east and an additional 2 pours to complete the north area. The entire project will use approximately 17,000 CY of concrete.
The first pour scheduled for in January 2016 used approximately 400 CY and took approximately 24 hours to complete. The setup time was affected by the cold temperatures.
[rev_slider alias=”Argos Concrete Pour”]
Video time-lapsed and not in real time.