By the time the construction phase of any new life science facility or expansion project wraps up, it can feel like the hardest part is over. But what many project owners realize too late is that unforeseen curveballs can appear in the later innings, especially when it comes to commissioning and operational readiness.
Our 2023 State of Life Sciences Capital Project Development research found that more than 8 in 10 project owners have experienced delays and cost overruns, issues that can feel inevitable when tackling these complex, highly regulated initiatives.
It doesn’t have to be that way.
Installation qualification (IQ) and operational qualification (OQ) are critical steps in the commissioning phase of any project, and also those most prone to inefficiencies. Nuanced regulatory requirements, reactive planning, and traditional commissioning approaches quickly overcomplicate this process.
The right upfront communication and collaboration, however, can expedite IQ and OQ—getting life sciences organizations into production faster, saving time and resources throughout.
Below is a high-level summary of what is covered in our on-demand webinar: Streamlining IQ/OQ for an Efficient Delivery.
6 Barriers to IQ/OQ Efficiency
A variety of challenges impact the speed and ease of IQ/OQ. In our on-demand webinar, we explore six main barriers and ways to overcome each of the following:
1
Commissioning and validation overlap: Many projects still suffer from repetitive testing. Once facilities are turned over and clients begin qualification testing and validation, they’re actually duplicating many of the tests previously handled during commissioning. But under the more recently rolled out ASTM E2500 standards, QA can be brought into the process during commissioning (mitigating the need for repeat tests later on).
2
Rigid testing timelines: Traditionally, installation qualification is followed by operational qualification and, finally, performance qualification. This sequential approach creates unnecessary bottlenecks—given the nature of IQ tests, there is no need to have them block OQ from starting sooner. Instead, most IQs (e.g., drawing and field checks) can begin before mechanical completion. Including less specificity in your test plans also creates valuable flexibility for commissioning teams to get IQ/OQ done quicker.
3
Data acquisition delays: A full roster of stakeholders are involved in the startup of any capital project such as general contractors, design-build teams, commissioning groups, and client maintenance teams—and everyone needs data from someone else to get their work done. The quicker you can get data into the CMMS, the better. For commissioning teams, this means collecting accurate asset data from the builder as early as possible, including unique IDs, manufacturer model and serial numbers, recommended maintenance information, and spare part numbers.
4
Lack of industry-specific builder knowledge: Builders know how to start up a new facility, but that doesn’t mean they are familiar with the nuanced documentation requirements that go into completing a life science facility. Commissioning teams should be brought in early to train and communicate with stakeholders before construction. so that everyone knows documentation requirements to satisfy FDA regulations. When possible, provide prior examples to demonstrate exactly what you’re looking for.
5
Resource constraints: Both on the client and vendor sides, bandwidth stands in the way of efficient IQ/OQ. General contractors may struggle to bring vendors on site to complete scope, delaying commissioning teams and forcing more work to happen in parallel. Client teams are already taxed for time, making it difficult to get timely approvals throughout a project’s life cycle. This underscores how crucial it is to communicate effectively and reduce the volume of testing (and approvals) happening simultaneously.
6
FDA approvals: Whether you are building out a new facility or expanding an existing one, there are steps you can take to expedite the FDA’s on-site audit. Start by studying similar manufacturing processes or devices that have already been approved and replicate their approach. Do not shy away from IQ/OQ templates either, which can speed up approvals compared to using documents that try to reinvent the wheel. You might also prioritize partial facility approvals, rather than waiting for an entire space to be delivered. The Q&A section of the Streamlining IQ/OQ for Efficient Delivery webinar, goes into a bit more detail about this.
In conclusion: Commissioning and operational readiness are often viewed as steps to worry about later in a capital project’s life cycle. But by planning these phases proactively and intentionally, project owners are more likely to reach their goals on time and on budget.
For more in-depth insights and tips into streamlining IQ/OQ, access our on-demand IQ/OQ webinar, or feel free to connect with one of our life sciences commissioning subject matter experts.