The 2023 State of Life Sciences Capital Project Development

Instant PDF
Download

One Click Access

Instant PDF
Download

One Click Access

Instant PDF
Download

One Click Access

PDF

Instant PDF Download

Introduction

Key Findings

Having a partner is critical—if you can source the right one. 86 percent of project owners say that hiring a qualified owner’s rep is key to a successful project, but 79 percent say finding the right owner’s rep can be challenging.

Capital project complexity is on the rise. 81 percent of project owners say their capital project goals will be more ambitious in 2024 compared to 2023.

User requirements can make or break project outcomes. 89 percent of project owners say that defining user requirements for a project is key, but only 38 percent are sure they’re accurately defining the scope.

Getting more done, cost efficiently. Project owners’ top objectives for 2024 and beyond are lowering the cost per square foot and increasing the number of completed projects.

Capital Projects Plans & Risks

Despite the very real risks of schedule delays and cost overruns, a new wave of life sciences capital projects is expected to crest over the next six to 12 months. Step one in these initiatives — defining user requirements — is often the most fraught, and where project owners need critical support.

Facilities are high-risk projects

New capital projects are important in the short term

89%

of project owners say that the design and construction of a new life sciences capital project can become a serious financial risk to their company if it goes over budget and schedule

87%

of project owners say beginning a new capital project initiative is one of their company’s top priorities in the next 6-12 months

Deadline Delays Are Highly Common

0%
of project owners have experienced significant to moderate deadline delays on their projects

Defining User Requirements Is Crucial But Elusive

0%
of project owners say that defining user requirements for a project is key, but only 38% are sure they’re accurately defining the scope

Cost Overruns Are Frequent And Significant

0%
of project owners have experienced significant to moderate cost overruns on their projects

Project Owners’ Top Financial Concerns

Myriad challenges can derail a capital project, but at the end of the day it’s the financial impact of those challenges that matters most. In the current economic climate, labor shortages and surging costs of materials pose the greatest threat to project success.

COST OVERRUNS ARE THE MOST PROBLEMATIC ISSUE FOR PROJECT OWNERS

The top pain points for project owners are:

  • Cost overruns 
  • Delays in permitting 
  • Lack of qualified contractors 
  • Delays in construction 
  • Managing change orders 

LABOR COSTS CAN DERAIL A PROJECT FOR OWNERS

The top risks that project owners face are:

  • Changes in labor costs
  • Changes in materials costs
  • Unforeseen weather conditions
  • Delays in permitting
  • Changes in labor availability

MATERIAL AND LABOR COSTS ARE THE MOST COMMON DRIVERS OF BUDGET OVERRUNS

The top five reasons for budget overruns are:

  • Changes in materials costs
  • Changes in labor costs
  • Delays in construction
  • Unrealistic preliminary budget
  • Delays in permitting

Owner’s Rep Perceptions

Strategic support from an external owner’s rep can be the deciding factor between a delayed, over-budget project and an on-time, successful facility turnover. The most in-demand owner’s reps offer end-to-end expertise in every stage of the project life cycle—but finding the right partner takes effort.

Finding the right owner’s rep is a challenge

0%

of project owners say that hiring a qualified owner’s rep is key to ensuring a successful project, but…

0%

say finding the right owner’s rep can be challenging

A Successful Owner’s Rep Integrates Every Aspect Of A Project

Majority Of Project Owners Likely To Use Owner’s Reps As First Point Of Contact For New Projects

0%

of project owners say that having an owner’s rep who integrates every aspect of project delivery from concept to operational readiness is vital to the success of the project

0%

of project owners who began capital projects with an owner’s rep on previous projects say they want to work with another one on future projects

The top benefits of working with an owner’s rep according to project owners:

  • Cost control

  • Consistency and standardization

  • Project schedule management

  • Quality assurance

  • Scope development assistance and management

The top qualities project owners seek in an owner’s rep partner include:

  • Proven process for integrated project delivery

  • In-house capabilities of program, project, and construction management, as well as commissioning and operational readiness

  • Clear and streamlined stakeholder communication

Delivery Methods

Pulling in outside help mid-project, and distributing work across multiple parties, puts capital projects at greater risk of time and cost overruns. Most project owners want a partner who can support design-build delivery from day one.

DESIGN-BUILD AND CMAR ARE PREFERRED DELIVERY METHODS

The preferred delivery method of life sciences capital project owners is:

*Tied for top method, each at 29%.

CONSULTANT-LED DESIGN-BUILD DELIVERY IS A PROJECT BOOST

85%

of project owners who have used a consultant-led design-build delivery method say it saved them time, budget, and stress

DESIGN-BUILD PROJECT DELIVERY SIMPLIFIES PROJECTS

According to

86%

of project owners, having a highly technical, end-to-end service partner that offers one contract, one point of contact, and one price is key to simplifying their project

Top Challenges of Programming and Design to Construction, Cx, & Operational Readiness

Preconstruction activities, namely budgeting and scheduling, are the most complicated parts of facility programming—yet the most critical to get right.

INITIAL BUDGETING PROVES TO BE MOST COMPLEX PART OF FACILITY PROGRAMMING

The most challenging aspects of programming for a new facility:

COST CONTROLS ADD THE MOST COMPLEXITY TO NEW CONSTRUCTION

The most challenging aspects of construction for a new facility:

  • Cost control
  • Quality control
  • Schedule control
  • Safety
  • Construction management

BUDGET AND SCHEDULING ARE THE MOST COMPLEX DESIGN ASPECTS

The most challenging aspects of design for a new facility:

  • Budget/Schedule
  • Basis of design
  • Development of user requirements
  • Project controls
  • Design program and scope

BUILDING AUTOMATION IS A CHALLENGE FOR NEW FACILITY COMMISSIONING

The most challenging aspects of commissioning for a new facility:

PREDICTIVE/PREVENTATIVE/CORRECTIVE MAINTENANCE IS THE GREATEST CHALLENGE FOR OPERATIONAL READINESS

The most challenging aspects of operational readiness for a new facility:

  • Predictive/Preventative/Corrective maintenance
  • Calibration programs
  • Maintenance program SOPs
  • Final data verification
  • Spare parts and inventory identification

A Look Ahead To 2024 And Beyond

Despite funding challenges and an uncertain macroeconomic climate, the outlook for the life sciences sector is still promising. Aging populations are driving demand for advanced treatments, and the U.S. clinical trials market is expected to swell from $26 billion in 2023 to nearly $40 billion by 2032. But these positive indicators don’t eliminate the need for life sciences organizations to adapt.

2024 is lining up to be bigger than 2023.

81%

of project owners say their capital project goals will be more ambitious in 2024 compared to 2023. 

LOWERING THE COST PER SQUARE FOOT AND INCREASING NUMBER OF PROJECTS ARE TOP OBJECTIVES OF PROJECT OWNERS

BIOTECH WILL BE THE MOST ACTIVE INDUSTRY FOR CONSTRUCTION OVER THE SHORT TERM

BIOTECH WILL BE THE MOST ACTIVE INDUSTRY FOR RENOVATION OVER THE SHORT TERM

LOWERING THE COST PER SQUARE FOOT AND INCREASING NUMBER OF PROJECTS ARE TOP OBJECTIVES OF PROJECT OWNERS

How project owners are defining their top goals:

  • Lower cost per square foot
  • Increasing the number of projects to be completed
  • Increasing budgets to manage
  • Better budget management (Efficiencies)
  • Faster speed to market

BIOTECH WILL BE THE MOST ACTIVE INDUSTRY FOR CONSTRUCTION OVER THE SHORT TERM

The top life sciences facilities being built within the next 3 years:

  • Biotech
  • Research and development
  • Clinical research
  • Pharmaceutical
  • Medical device

BIOTECH WILL BE THE MOST ACTIVE INDUSTRY FOR RENOVATION OVER THE SHORT TERM

The top life sciences facilities being renovated within the next 3 years:

  • Biotech
  • Medical device
  • Pharmaceutical
  • Clinical research
  • Research and development

Better strategic planning is how project owners plan to overcome setbacks

The top ways project owners are solving their toughest challenges:

  • Improved planning and strategy
  • Improved communication and technology
  • Working with an owner’s rep as a first point of contact
  • Improved progress monitoring
  • Working with a full-service design-build firm

CAPITAL BUDGETS ARE EXPECTED TO RISE STEADILY OVER THE SHORT TERM

20 percent of project owners say their capital budgets will increase in 2024, a number that grows to 31% in 2025 and 37% in 2026.

MORE EXPENSIVE MATERIALS IS SET TO BE A LARGE ISSUE OVER THE LONGER TERM

The biggest challenges to project owners over the next 5 years will be:

  • Rising cost of materials
  • Increasing complexity of life sciences facilities
  • Supply chain delays
  • Shortage of skilled labor
  • Changing regulatory environment

Conclusion

Building a large-scale life science facility is a significant investment, one prone to incredible risk and uncontrollable external factors. But the process does not have to be intimidating.

As project owners anticipate even more initiatives launching in 2024—while facing the always-on pressure of maintaining cost efficiency—external, expert support will be non-negotiable. Project owners have many options when it comes to simplifying this work, but it takes skills, experience, and the right guidance to get it right.

The ability to successfully turnaround new facilities is becoming a competitive differentiator for life sciences firms. With the right support (engaged at the right time), project owners can move from construction to operational readiness faster and with fewer surprises.

Challenges like funding, supply chain delays, and labor shortages will always be somewhat outside of project owners’ control. However, lining up the right resources and partners from the start is not.

Research Methodology

35 North commissioned an independent market research study of 328 capital project owners and leaders working in life sciences facility development about the trends, opportunities, challenges, and new solutions that affect their success. All respondents are responsible for the planning or construction of facilities for their life sciences organization.

Respondent Breakout by Industry

About 35 North

35 North is a construction services consulting firm that specializes in developing life sciences capital projects. Partnering with project owners, we provide the technical expertise and ability to streamline projects as an owner’s representative, by customizing a combination of services, or by providing end-to-end services – from idea to operational readiness.