US Department of Veterans Affairs

U.S. Department of Veterans Affairs

VA Medical Center Jesse Brown Steam and Chilled Water Study

CHICAGO, ILLINOIS

The steam and chilled water study consisted of the phased replacement of the steam/condensate distribution piping and chilled water piping, including pipe supports, insulation and jacketing, and valves.

35 North provided cost management services for the evaluation of this project, which consisted of the steam pressure reducing stations and assessment of the steam/condensate and chilled water distribution system. The project scope also included evaluating the chilled water supply piping and condensate receiving units, as well as phasing measures. Additional add alternates included the insertion electromagnetic flow meter and hot tap, pressure and temperature gauges, and the installation of 2-300 ton air-cooled chillers to serve Building 40.

PROJECT VALUE
$3.2 Million

OUR ROLE

  • Cost Estimating

MARKET SEGMENTS

  • Healthcare
  • Government
Let us put our expertise to work for you

We’re excited to partner with you! Our business consulting services and expertise in construction and project management are second to none. Our success is driven by the decisions we make, the policies we implement, and how our employees are trained.

Ready to
get started?

Cost Estimation and Project Management - Contact 35 North

Ready to get started?

What our clients are saying